| |
|
| |

Prudential Overall Supply |
11,000 SF, Building
Addition, Round Rock, TX
Owner: Prudential Overall Supply Co.
Architect: Agee Engineering, Inc.
Start/Complete: 10/03 - 04/04
Method of Delivery: Bid
The Prudential Overall Supply project consisted of a 11,000
SF clean-room laundry facility expansion. Bartlett Cocke maintained
full operations throughout the 4 month construction period.
This project included an on-site water treatment facility, to
treat the effluent created by the laundering process. This facility
will be the main cleaning facility of clean-room jump suits
used in the Semiconductor industry in Austin, Texas, and surrounding
areas. |
|
 |


Toyota Motor Manufacturing Texas
|
2,000,000 SF New Toyota
Assembly Plant, San Antonio, TX
Owner: Toyota Motor Manufacturing Texas
Architect: SSOE/Marmon Mok
Start/Completion: 06/04 - 05/06
Method of Delivery: Select Bid
Toyota’s main plant is comprised of nine main areas that
were awarded to the Walbridge/Bartlett Cocke Joint Venture:
• Foundations - Assembly,
Press, Weld, Plant Office 1,225,000 SF
• GC Package - Assembly, Press, Weld, Plant Office 1,225,000
SF
• Sitework II –
9 miles of pipe and 4 miles of Asphalt
• Plastics – 65,000 SF
• Tsusho – 305,000Sf
• Audit Lab / Oil Stores – 43,000 SF
• Test Track – 30 acres + 2,775 SF paddock building
• Visitor / Reception
– 40,600 SF
•
Kautex (Design/Build Supplier Buildings)
Walbridge Aldinger/Bartlett Cocke General Contractors joint
venture, under separate contract, performed the foundation work
for the Assembly, Plant Office and Press/Weld buildings from
July to November 2004. Approximately 750 building piers were
installed to a depth of 32 feet below grade and 31,000 cu of
concrete, on 2,200 tons of reinforcing steel. The Project consisted
of Sitework, caissons, press pits and tunnel, and slab-on-ground
preparation.
Walbridge Aldinger/Bartlett Cocke General Contractors joint
venture was then awarded the contract to build the Assembly
Plant, Plant Office and the Press/Weld Building. The Schedule
commenced in December 2004 and was completed August 2005.
The Press building includes the metal sheets receiving area
and press pits, where metal components (bumpers, tailgates,
fenders, hoods, etc.) are stamped and presses. The Weld building
is where these parts (bumpers, tailgates, fenders, hoods, etc.)
are welded together. The Assembly building is where
the total and final product is assembled. The Plant Office
is the central hub for the entire facility, acting as the control
station. The scope of the work completed for all four areas
includes: earthwork/excavation, misc. concrete, masonry block,
misc. metals, structural steel and joists, metal roof and floor
decks, cold formed metal framing, gypsum board framing, acoustical
tile ceilings, rough and finish carpentry, HM doors and frames,
wood doors, aluminum doors and frames, hardware, metal wall
panel systems, single-ply membrane roofing, insulation, sealants,
OH coiling doors, sectional OH doors, high-speed roll-up fabric
doors, loading dock equipment, air shower, hydraulic elevator,
bridge cranes and wall traveling cranes, plumbing, HVAC, fire
protection and electrical.
The Sitework II Package began February 2005 and was completed
in August 2005. This project consisted of providing and installation
of underground utility services. Other scopes of work included
Earthwork, grading, mulching, spreading of topsoil, seeding,
watering, maintenance, chain link fencing, asphalt and concrete
paving. The Plastics building is a single, slab-on-grade
facility. Included in the construction were IMM pits, trench
drain systems, blast relief walls, metal siding exterior, fire
protection, bridge crane and a HVAC system. This building facilitates
the production of plastic components for the Toyota vehicles.
The design for this Toyota plant included an 18-tier/one (1)
supplier to be located on the plant site. Of the 18, the Toyota
Tsusho project consists of seven (7) suppliers that are
housed in 5 different buildings. The main facility is for
steel coils which will be cut into sheets to be pressed into
different vehicular components (bumpers, tailgates, fenders,
hoods, etc.) Two (2) buildings are recycling centers and one (1) building
will make the exhaust systems for the vehicles at the manufacturing
plant. The final building constructed is used as an office for the
suppliers.
The final three projects that were awarded to the Walbridge/Bartlett
Cocke Joint Venture were the Audit Lab & Oil stores, Test
Track and the Visitor/Receptions building. The Audit Lab &
Oil stores consisted of two pre-engineered metal buildings,
slab-on-grade, trench drain systems, pits, blast resistant area,
masonry partitions, metal siding exterior, metal roof, MEP trestle,
HVAC system. For visitors, Toyota has included a Reception and
Visitors facility. The Reception building has several conference
rooms for meetings and presentations, offices and an exhibit
room. It also has an instruction safety room, both men’s
and women’s restrooms and several storage rooms. Where
as the Visitor’s Center contains a lobby, motor vehicle
showroom, several conference rooms and offices.
The Test Track is used for testing vehicles coming off the assembly line. It includes a 2 mile asphalt track loop (with sound
isolation area), an evaluation area for testing different aspects
of the vehicles, a small shop building and an access road from
the plant (with a pre-cast bridge over rail lines). The evaluation
area requires several unique areas: Belgian block road, sine
wave road, platform road, speed bump, rough pavement road, rope
road, sope road and a skid pad. |
| |
 |

HEB Produce |
166,000 SF, New Produce Facility
Owner: H.E. Butt Grocery Corporation
Architect: Setter, Leach & Lindstrom, Inc.
Completion: 07/93
The H.E. Butt Grocery Produce Facility was successfully constructed
on an accelerated six (6) month schedule and the project consisted
of a 166,000 square foot storage and ripening facility. With
a start date of February 13, 1993, this project was delivered
in 6 months, with a July 15, 1993 completion date. Building
methods utilized for construction included a over excavated
slab on grade foundation, structural steel frame, and metal
panel and CMU exterior wall system. Special features of this
project include: extensive refrigeration rooms, banana ripening
rooms, high-bay storage areas, office facilities, and a super
flat concrete floor that was tested for floor flatness and floor
levelness. |
|
 |

Block Distribution |
371,000 SF, New Headquarters & Distribution
Facility
San Antonio, Texas
Owner: Block Distributing Company
Architect: RVK, Inc.
Method of Delivery: Bid
Start/Completion: 09/00 - 08/01
The Block Distribution Center project located in the Tri-County
Park in Schertz, consists of 370,000 SF of warehouse/office
space. This facility serves as Block's corporate headquarters
and primary distribution center of wine and spirits throughout
central and south Texas. The building consists of a drilled
pier foundation, slab on grade, and tilt-wall structure. The
building pad required a minimum of ten (10) feet of crushed
limestone, and the built-up roof structure covers an area of
nearly 8.5 acres. The exterior of the office area was finished
using oversized burnished masonry block, which gives it the
appearance of cut limestone. And the entrance to the office
features an attractive curved slate facade.
In order for forklifts to move and hoist loads up to 30 feet
above finished floor safely, there were strict floor flatness
and levelness standards established. The Floor Flatness specification
established was FF-50 and the Floor Levelness specification
was FL-30. To verify proper installation, a materials engineer
tested the Floor Flatness and Floor Levelness, no later than
72 hours after the concrete was placed and finished. The major
challenge on the project was schedule. This project had a specified
11-month "date certain" completion, and the contract
stipulated that the warehouse space must be released within
9-months, so that a computerized laser, conveyor system and
storage racking system could be installed before the final completion
date. This aggressive schedule required 10-12 hour work days,
6-7 days a week, to meet the proposed deadline. Bartlett Cocke
General Contractors undertook an aggressive fast-track project
in the construction of the new Block Distribution Center. |
|
 |

Jaffe Aerospace Corporation |
125,000 SF, Hangar Space for 2-707’s,
Office & Shop
Owner: Jaffe Aerospace Corp.
Architect: W.E. Simpson Co., Inc.
Completed: 06/88
The Jaffe Aerospace corporation project was a fixed base operator
(FBO) facility located at the San Antonio International Airport
that was completed under the Design/Build project delivery method.
This FBO facility included a large hangar space for two (2)
707’s, office space and shop space. Specific amenities
included facilities for aircraft fueling, aircraft tie-down,
aircraft parking, aircraft maintenance, and ground services.
The project consisted of a 125,000 SF pre-engineered
metal building that was supported by a drilled pier foundation.
This project also included significant amounts of concrete paved
apron that accommodated aircraft parking and tie-downs, with
taxi-out capability including sufficient taxi clearances. The
MEP systems utilized for this project included roof-top HVAC
units and standard minimum electrical power requirements. |
|
| |
|
|